Estimate how much filler metal a weld takes and what it costs, by bead size, length and process: MIG/MAG, stick, flux-cored or TIG.

  • Free
  • No sign-up
  • Runs in your browser

Inputs

Unit system
Joint
Joint type
mm
m
%
Material and process
%
kg/h
%

Arc time over total time.

L/min

0 for stick and self-shielded wire.

Costs
/kg
/m³
/h

Result

Filler to buy

1.636kg

Weld section
19.8mm²
Deposited per meter
0.1554kg/m
Total deposited
1.554kg
Arc time
0.62 h
Total work time
1.55 h
Gas
0.56m³

Formula

Filler = Section × Density × Length ÷ Efficiency

Reference values for a starting point: replace them with your wire's datasheet and your shop's times.

Pro feature

Same length with other leg sizes

LegPer meterFillervs. yours
3 mm0.0389 kg/m0.409 kg× 0.25
4 mm0.0691 kg/m0.727 kg× 0.44
5 mm0.1079 kg/m1.136 kg× 0.69
6 mm0.1554 kg/m1.636 kg× 1
8 mm0.2763 kg/m2.909 kg× 1.78
10 mm0.4318 kg/m4.545 kg× 2.78

Results are estimates and should be verified for critical engineering or manufacturing applications.

How it works

Choose the joint, the bead size, the length and the process. The calculator gives the weld metal deposited, the filler you need to buy, the arc and work time and, if you enter prices, the cost per meter and in total.

Each process loads an efficiency, a deposition rate, an operating factor and a gas flow as a starting point. They vary a lot with the wire, current and position, so replace them with your datasheet and your shop's times. This is an estimate for quoting, not a welding procedure.

Formula

  • Fillet area = Leg² ÷ 2
  • V butt area = t² × tan(Angle ÷ 2) + Gap × t
  • kg per meter = Area (mm²) × (1 + Reinforcement) × Density (g/cm³) ÷ 1000
  • Filler = Deposited weight ÷ Efficiency
  • Arc time = Deposited weight ÷ Deposition rate
  • Total time = Arc time ÷ Operating factor
  • Gas (m³) = Arc time (h) × Flow (L/min) × 60 ÷ 1000

Example

10 m of 6 mm fillet in carbon steel with MIG, no reinforcement, 95% efficiency

  1. 1Area = 6² ÷ 2 = 18 mm²
  2. 2Deposited = 18 × 7.85 ÷ 1000 = 0.1413 kg/m → 1.413 kg in 10 m
  3. 3Filler = 1.413 ÷ 0.95 = 1.487 kg
  4. 4Arc time = 1.413 ÷ 2.5 = 0.565 h; total at 40% = 1.413 h
  5. 5Gas = 0.565 × 15 × 60 ÷ 1000 = 0.509 m³

About 1.49 kg of wire, 1.41 hours of work and 0.51 m³ of gas.

Assumptions, sources and review

Assumptions and limitations

  • Fillet area = leg² ÷ 2; single-V area = t² × tan(angle ÷ 2) + gap × t, with the total included angle and no root face. The cap is covered by the reinforcement percentage.
  • Default efficiency: stick 60%, MIG/MAG 95%, flux-cored 83%, TIG 91%.
  • Default operating factor: stick 25%, MIG/MAG 40%, flux-cored 40%, TIG 30%, inside TWI's ranges. Set-up and assembly time are not included.
  • Default deposition rates (stick 1.2, MIG/MAG 2.5, flux-cored 3, TIG 1 kg/h) are within published process ranges, but no source gives a typical shop value: they are editable starting points.
  • Default gas flow: MIG/MAG and gas-shielded flux-cored 15 L/min, TIG 10 L/min, stick 0. Set 0 for self-shielded wire.
  • Densities: carbon steel 7.85, stainless 7.93 and aluminum 2.70 g/cm³. Estimate for quoting, not a welding procedure.

The formula and the worked example on this page are checked by automated tests in Oxenly's code.

Last reviewed on November 22, 2026 by Diego Urtado.

Found an error? Report it

Frequently asked questions

Why does a slightly bigger fillet cost so much more?

Because the section grows with the square of the leg. Going from 3 to 6 mm doubles the leg but makes the section, the filler and the arc time four times larger.

What is deposition efficiency?

The share of the filler you buy that ends up in the weld. The rest is lost as spatter, slag and, with stick electrodes, the stub you throw away.

What is the operating factor?

The share of working time the arc is actually on. The rest goes to positioning, cleaning, changing electrodes and handling parts.

Can I use it as a welding procedure?

No. It estimates material, time and cost for quoting. Weld size, process and parameters must come from your design and qualified procedures.